← All insights
Funding & Incentives

New Jersey Set a Price for Battery Incentives. Commercial Buildings Are Not In It Yet.

New Jersey has finally put a price on its program to pay for batteries at private property. If you own or manage a commercial building, that price does not apply to you, and it is worth understanding exactly why before you budget anything around it.

On August 17, 2026 the Board of Public Utilities released what it calls a straw proposal, meaning a draft program design published for public comment rather than a final rule, for the Garden State Energy Storage Program Phase 2, Block 1 (GSESP Phase 2 Block 1 Straw Proposal). The state held a public meeting on September 3 and took written comments through September 10 (NJBPU public notices). That comment window is now closed, so the design described below is close to what the Board will act on.

What the state actually proposed

Block 1 would pay up to $200 per kilowatt per year, for ten years, to customers who install a new battery at their property. The target is 150 megawatts of new battery capacity statewide, handed out first come, first served until it runs out. There is a $50 application fee per project.

What those terms actually mean

A few pieces of this need translating, because the program hinges on them.

  • Behind the meter. The battery has to sit on your side of the utility meter, wired into your building's electrical system, not connected directly to the grid as its own power plant. Grid-side projects are shut out of Block 1 entirely.
  • Awarded Storage Capacity. The battery's power rating in kilowatts, meaning how fast it can push power out, not how much energy it holds. The payment is calculated on this number.
  • Performance Factor. This is the part that decides what you actually get paid. The utility calls dispatch events, meaning it tells your battery to discharge during expensive grid hours. The Performance Factor measures how much your battery actually delivered against what it promised. Your payment is scaled by it.
  • EDC. The state's term for your electric utility. In our service area, PSE&G, JCP&L, or Orange and Rockland.

The utility can call on the battery up to 35 times a year, for up to four hours per event, with two hours of notice for a normal event and as little as ten minutes in an emergency.

The headline number is not the check

This part comes from the state's own worked example rather than from us. The proposal walks through a sample battery rated at 11.5 kilowatts. At $200 per kilowatt, the most that battery could earn is roughly $2,300 a year. The state's own example pays $540, because it assumes a Performance Factor of 23.5 percent.

The state modeled a real battery earning less than a quarter of the advertised rate and put that arithmetic in its own proposal. The $200 figure is a ceiling only a project at 100 percent performance would reach. Anyone quoting you the ceiling as income is either not reading the document or hoping you will not.

Commercial buildings are not in Block 1

The proposal states that eligibility "is limited to residential customers." Commercial and industrial buildings are not eligible for Block 1 as written.

Two qualifications matter. First, the Board asked stakeholders whether to allow small commercial customers into Block 1. It did not decide, and we do not know how the comments landed. Second, the Board says it intends to use this framework to build "subsequent near-term storage deployment opportunities that would provide compensation for C and I scale" batteries "at critical facilities," meaning commercial and industrial buildings whose power cannot go down.

That last line is worth watching if you run a medical office, an emergency responder facility, or anything with patients or refrigeration in it. But watch it with your eyes open. There is no date, no dollar figure, and no eligibility rule published for that commercial program. It is a stated intention, not a budget line.

If you need a battery for a charging project, the money is somewhere else

We wrote last week about the NJEDA requiring Take Charge projects to include solar panels or a battery on site. The obvious follow-up was who pays for that battery. The answer is not GSESP. It is Take Charge itself.

The Take Charge program page lists on-site battery systems that provide or store power for the chargers as an eligible cost, capped so that this category cannot exceed 60 percent of total eligible project cost. Awards reimburse at least 50 percent of eligible costs, with a $100,000 minimum per project and a $5 million maximum per EIN, meaning per business tax identification number rather than per building. Applications are not open yet. The page says notice will be given when they are.

So for a commercial charging project, the battery is fundable through the charging grant, not the battery program. Different applications, different agencies, different rules.

The federal side moved too

The federal tax credit for EV charging equipment, Section 30C, terminated for anything placed in service after June 30, 2026 (26 U.S.C. 30C). If your project math still carries that credit, it is stale.

The clean electricity investment credit under Section 48E does still cover energy storage technology placed in service after December 31, 2024. The IRS puts the base credit at 6 percent of qualified investment, rising to as much as 30 percent for projects meeting prevailing wage and registered apprenticeship requirements (IRS, Clean Electricity Investment Credit). Prevailing wage means paying the published government wage rate for that trade and county. Registered apprenticeship means a set share of labor hours goes to apprentices in a registered program. As an IBEW Local 164 signatory contractor we meet both as a matter of course, but whether your project qualifies, and at what rate, is a question for your tax advisor.

What we would do right now

If a battery is in your plans, three things are worth doing now.

  1. Find out what your existing electrical service can actually carry. Every one of these programs assumes you know. Batteries, chargers, and heat pumps all land on the same service, and that answer decides whether your project is a panel change or a utility transformer job with a year attached to it.
  2. Get the interconnection application moving. Block 1 would require an active and valid interconnection application, meaning the formal request to your utility for permission to connect equipment that pushes power, at the time you apply. Utility review is not fast. Being in the queue is not the same as being approved.
  3. Do not buy equipment against an unwritten rebate. Only new batteries qualify under Block 1. Retrofits, expansions, and anything already running are excluded unless future guidance says otherwise. Installing early to get ahead of a commercial program that does not exist yet is the most likely way to disqualify yourself from it.

The timeline, as the state describes it

The proposal lays out its own schedule, and it is long. Board Staff expects to bring the order establishing the program design in October 2026. Utilities file implementation petitions in December 2026. Block 1 is anticipated to open in July 2027. The state's planning table then shows 50 megawatts deployed by July 2028, 100 by May 2029, and 150 by February 2030.

That is the residential program, the one that is actually designed. The commercial version sits behind it. Plan accordingly, and treat any commercial battery incentive as money that does not exist until there is an order with a number in it.

Program details in this article are drawn from the NJBPU GSESP Phase 2, Block 1 Straw Proposal dated August 17, 2026, the NJBPU public notices page, the NJEDA Take Charge program page, and IRS and United States Code materials, all as of September 14, 2026. Block 1 is a proposal under Docket QO26040116, not a final program. Comments closed September 10, 2026 and the Board has not issued an order, so every figure here can change. We have not confirmed whether small commercial customers will be admitted to Block 1, and no eligibility rules, funding amount, or schedule have been published for the commercial and industrial program the Board says it intends to build next. Verify current terms with NJBPU at nj.gov/bpu and with the NJEDA at takecharge@njeda.gov before making a decision.

Working on something this touches?

We estimate, permit, and self-perform this work across Bergen, Hudson, Essex, and Passaic counties.

Request a bid

More briefs

Start here

Send us the drawings. We’ll tell you what we see.

Bids, budgets, value-engineering reviews, and service calls all start the same way: a short conversation with the person who will actually run the work.